"Best engineering team for the design of comfortable, safe, and environment-friendly roads"
Road network can be compared to the blood vessels in human body.
National traffic network needs to be systematic and harmonious in order to achieve the growth of the nation, just as the circulation of blood in human body needs to be harmonious for the good health, Construction of comfortable and safe roads is extremely important for the balanced growth of the country and enhancement of the convenience of the people.
The road planning & design team is pursuing the best design for the road construction in order for everyone to use them safely and comfortably, and Seoyoung is a top class in the area of road design in Korea.
The road planning & design team of Seoyoung is equipped with experiences and performance in a diverse range of areas including feasibility study, preliminary design and detailed design as well as T/K, alternative design and private investment projects. We are dedicated to provide the highest quality works through professional and systematical executions with high level of responsibilities based on our professional and systematical we accumulated and ceaseless researches thus far.
The road planning & design team of Seoyoung Engineering Co., Ltd. Shall reward our clients by producing the best performances through continuously challenging and pioneering ideas with foremost priority on the satisfaction of the clients.
Incheon Bridge is the longest cable-stayed bridge in Korea and the 5th longest in the world with the main span of 800m. It was constructed to achieve the goal of becoming a hub country for economy and transportation logistics in Northeast Asia. The construction services as the alternative route for the New Airport Expressway in the event of emergency situations as well as improves the accessibility to the Incheon International Airport from the southern regions of Seoul.
We accumulated technological capabilities and know-how through the construction of the longest span cable stayed bridge in Korea and one of the longest in the world. It is the project left the longest maritime bridge with the total length of 11.6km. Behind numerous historical footsteps including the format of the execution, design, construction and maintenance of the project.
It is a project that was accomplished through foreign investment when Korea was confronted with nation-wide economic difficulties due to the IMF financial crisis. The construction period was substantially shortened through the application of the FAST TRACK construction format technologically was implemented Limit State Design used in many advanced countries. With the application of the viscoplastic design based on the static load test of large diameter piles. And collision protection design from vessel impact all accident.
In addition, it was possible to complete the construction of the maritime bridge with length of more than 10km within 5 years by manufacturing and installing the structures through automated manufacturing processes for the majority of the construction processes including the application of FSLM construction for the first time in Korea. This project completion resulted in the honor of being selected as one of the ’10 most amazing construction projects in the world’ by the [Construction News], a newspaper specializing in the area of construction of England.
Overview of Project
Project name: Construction of Incheon Bridge
Location: General region of seashore boulevard of Yeongjongdo ~ General region of Songdo landfill
Area (length): 12.3Km
Duration of project: July 1, 2005~October 16, 2009
Client: Incheon Bridge Co., Ltd.